A HR manager looks up the National Card, sees that the authority decides in twenty-one days, and builds a start date around it. Three months later the employee still cannot begin.

Nobody misled them. The twenty-one days is the correct figure, published by the authority, and the authority did not break it. The number simply does not measure what the reader assumed it measures.

What the law actually says

These are the statutory processing deadlines for the permits an employer is most likely to encounter:

Permit Statutory deadline What we see in practice
Residence permit for employment 70 days 70–90 days
EU Blue Card 70–90 days 60–70 days
Hungarian Card 70 days 60–70 days
Intra-corporate transfer 70 days 60–70 days
National Card 21 days 70–90 days
Family reunification 21 days 60–70 days

Read the table for a moment. Four of the six land roughly where the law says they will. The two that do not are the two with the shortest deadlines — and they are out by a factor of three.

The clock stops, and the law says it may

The deadline does not run continuously from filing to decision. Hungarian immigration law is explicit about this:

The period for remedying deficiencies — submitting missing documents — and the time taken for various other procedural steps is not included in the processing deadline.

So the twenty-one days are twenty-one days of the authority working on the file. They are not twenty-one days on a calendar. Every time something is missing, the clock stops until it arrives. Every time the case is suspended for a reason set out in law, that period does not count either.

This is not a loophole and it is not the authority being difficult. It is how administrative deadlines work in Hungarian law generally. But it means the published figure answers a different question from the one an HR team is asking. The authority is telling you how much of its own time the case may take. You want to know what date to write in a contract.

Family reunification: the clearest example

A family case shows the mechanism in its purest form. When an employee brings a spouse and children, the family members cannot be decided before the employee is. The employee is the one who supports them, so their eligibility depends on his or her status being settled first.

So the family cases are suspended. The authority prepares the sponsor’s permit, and while that runs, the family files sit — legally, correctly, and with the clock stopped. When the sponsor is decided, the family follows, often in the same batch.

Twenty-one days of processing. Two to two and a half months on a calendar. Both numbers are true.

The National Card: the same rule, a different cause

The National Card is available to nationals of eight countries and needs no labour market test, which makes it one of the faster permits on paper. In practice it is currently the slowest of the five.

The reason is workload. The Budapest office is heavily loaded, and files are transferred out to county authorities — Szeged, for instance — to be decided there. The transfer itself is not misconduct and it is not counted against the deadline, but on a calendar it can add weeks.

It is also worth knowing that county authorities do not all read the same rules identically. Where a case is decided affects how it is decided, and that is not something an applicant chooses.

What this means for planning

The practical answer is not to distrust the published deadlines. It is to stop using them as a planning number.

4 to 5 monthsFrom the decision to hire to the day the employee can legally start. This is the number to plan against, not the statutory deadline.
5 to 6 monthsBefore a permit expires, a renewal conversation has to start. We flag the date; the company then has two to four weeks to settle whether the person stays and whether the salary or the role changes.
2 to 3 weeksWhat an apostille and a certified translation typically take. This happens before the file is even complete, and it is outside everyone’s control.

The one thing an employer can control

Almost everything above is outside your hands. One thing is not.

The single largest cause of a stopped clock is an incomplete file — a missing document, a qualification that needs recognition, a salary figure that does not match the job classification. Each one triggers a request, and each request stops the deadline until the answer comes back.

A file that goes in complete is not a nicety. It is the difference between the published deadline being roughly right and being out by a factor of three.

Which is also why the useful conversation happens before the offer letter, not after it. By the time a start date is agreed, the questions that decide the timeline — where the qualification was earned, what the role is, what it pays, whether there is Hungarian or EU family — have already been answered by someone. They just have not been checked.

Planning a start date in Hungary?

Tell us who is arriving and by when, and we will tell you which permit applies and whether the date is realistic — including when it is not. The first call is free.

See also: which permit does your employee need and the HR manager’s guide to work permits in Hungary.